Rear extension and kitchen

A 1930s semi opened up with a timber-frame rear extension, new kitchen and full rewire.

Extension

Timber frame

Kitchen + rewire

Godalming

HANDED OVER

14

ON SITE

38 m²

FLOOR AREA ADDED

£80–120k

BUDGET BAND

6

TRADES ON THE JOB

THE BRIEF

More light, a kitchen that works, and no surprises on the invoice.

The back of the house was a dark galley kitchen and a lean-to nobody used. The Pearsons wanted one room for cooking, eating and homework, opening onto the garden, without moving out for half a year.

We proposed a timber-frame rear extension on a steel ridge beam, so the old back wall could come out in a single weekend. Ridge & Lane Architects drew it up, Brookfield Structures signed off the steel, and our own crew framed, rewired and fitted the kitchen.

WEEK 06

The old back wall came out on Saturday and the ridge beam is carrying everything as planned. The temporary kitchen stays in the dining room for three more weeks.

HOW IT WENT

14

weeks, start to snag.

01

Survey & drawings

WK 01–03

02

Groundworks & frame

WK 04–08

03

First fix & roof

WK 09–11

04

Kitchen, joinery & finish

WK 12–14

BEFORE / AFTER

BEFORE

↔

AFTER

“We lived through the whole build and never once had to chase anyone. The kitchen is where everyone ends up now, even the dog.”

woman and man wearing white sweater

The Pearsons

Godalming

·

Extension

NEXT PROJECT →

Loft conversion and oak stair

View project

Let’s build

something solid.

Book a site visit

CALL

01632 960 418

EMAIL

hello@joineryco.co.uk

VISIT

Hurst Farm Yard, Shalford

SOCIAL

Instagram · Houzz

© 2026 JOINERY · DEMO CONTENT

JOINERY

Rear extension and kitchen

A 1930s semi opened up with a timber-frame rear extension, new kitchen and full rewire.

Extension

Timber frame

Kitchen + rewire

Godalming

HANDED OVER

14

ON SITE

38 m²

FLOOR AREA ADDED

£80–120k

BUDGET BAND

6

TRADES ON THE JOB

THE BRIEF

More light, a kitchen that works, and no surprises on the invoice.

The back of the house was a dark galley kitchen and a lean-to nobody used. The Pearsons wanted one room for cooking, eating and homework, opening onto the garden, without moving out for half a year.

We proposed a timber-frame rear extension on a steel ridge beam, so the old back wall could come out in a single weekend. Ridge & Lane Architects drew it up, Brookfield Structures signed off the steel, and our own crew framed, rewired and fitted the kitchen.

WEEK 06

The old back wall came out on Saturday and the ridge beam is carrying everything as planned. The temporary kitchen stays in the dining room for three more weeks.

HOW IT WENT

14

weeks, start to snag.

01

Survey & drawings

WK 01–03

02

Groundworks & frame

WK 04–08

03

First fix & roof

WK 09–11

04

Kitchen, joinery & finish

WK 12–14

BEFORE / AFTER

↔

BEFORE

AFTER

“We lived through the whole build and never once had to chase anyone. The kitchen is where everyone ends up now, even the dog.”

The Pearsons

Godalming

·

Extension

NEXT PROJECT →

Loft conversion and oak stair

View project

Let’s build

something solid.

Book a site visit

CALL

01632 960 418

EMAIL

hello@joineryco.co.uk

VISIT

Hurst Farm Yard, Shalford

SOCIAL

Instagram · Houzz

© 2026 JOINERY · DEMO CONTENT

JOINERY

Rear extension and kitchen

A 1930s semi opened up with a timber-frame rear extension, new kitchen and full rewire.

Extension

Timber frame

Kitchen + rewire

Godalming

HANDED OVER

14

ON SITE

38 m²

FLOOR AREA ADDED

£80–120k

BUDGET BAND

6

TRADES ON THE JOB

THE BRIEF

More light, a kitchen that works, and no surprises on the invoice.

The back of the house was a dark galley kitchen and a lean-to nobody used. The Pearsons wanted one room for cooking, eating and homework, opening onto the garden, without moving out for half a year.

We proposed a timber-frame rear extension on a steel ridge beam, so the old back wall could come out in a single weekend. Ridge & Lane Architects drew it up, Brookfield Structures signed off the steel, and our own crew framed, rewired and fitted the kitchen.

WEEK 06

The old back wall came out on Saturday and the ridge beam is carrying everything as planned. The temporary kitchen stays in the dining room for three more weeks.

HOW IT WENT

14

weeks, start to snag.

01

Survey & drawings

WK 01–03

02

Groundworks & frame

WK 04–08

03

First fix & roof

WK 09–11

04

Kitchen, joinery & finish

WK 12–14

BEFORE / AFTER

↔

BEFORE

AFTER

“We lived through the whole build and never once had to chase anyone. The kitchen is where everyone ends up now, even the dog.”

The Pearsons

Godalming

·

Extension

NEXT PROJECT →

Loft conversion and oak stair

View project

Let’s build

something solid.

Book a site visit

CALL

01632 960 418

EMAIL

hello@joineryco.co.uk

VISIT

Hurst Farm Yard, Shalford

SOCIAL

Instagram · Houzz

© 2026 JOINERY · DEMO CONTENT

JOINERY

Create a free website with Framer, the website builder loved by startups, designers and agencies.