P—016
Timber-frame new build
A three-bed timber-frame home on a tight garden plot, built and clad by one crew.
New build
Timber frame
Full build + cladding
Cranleigh
HANDED OVER
32
ON SITE
140 m²
FLOOR AREA ADDED
£350–450k
BUDGET BAND
9
TRADES ON THE JOB
THE BRIEF
A whole house on a narrow plot, watertight before the autumn rain.
Mark and Helen Tate had planning for a family home at the end of a long garden, with neighbours on three sides and one narrow way in. Every delivery and every crane lift had to be planned to the hour.
We chose an open-panel timber frame so the shell could go up and be watertight in three weeks. Fernhill Studio led the design, Brookfield Structures detailed the frame, and our crew did the frame, roof, larch cladding and second fix.




WEEK 13
The frame is up and the roof is felted, so the house is now dry inside. The crane comes back on Thursday at 7am for the last lift, and we’ve told the neighbours.
HOW IT WENT
32
weeks, start to snag.
01
Survey & drawings
WK 01–06
02
Groundworks & frame
WK 07–18
03
First fix & roof
WK 19–24
04
Kitchen, joinery & finish
WK 25–32
BEFORE / AFTER


BEFORE
↔
AFTER

“We expected a new build to mean a year of stress, and it simply didn’t. Every Friday we got a note saying what had happened and what was next.”

Mark and Helen Tate
Cranleigh
·
New build
NEXT PROJECT →
Rear extension and kitchen
View project

Let’s build
something solid.
Book a site visit
CALL
01632 960 418
hello@joineryco.co.uk
VISIT
Hurst Farm Yard, Shalford
SOCIAL
Instagram · Houzz
© 2026 JOINERY · DEMO CONTENT
JOINERY


Timber-frame new build
A three-bed timber-frame home on a tight garden plot, built and clad by one crew.
New build
Timber frame
Full build + cladding
Cranleigh
HANDED OVER
32
ON SITE
140 m²
FLOOR AREA ADDED
£350–450k
BUDGET BAND
9
TRADES ON THE JOB
THE BRIEF
A whole house on a narrow plot, watertight before the autumn rain.
Mark and Helen Tate had planning for a family home at the end of a long garden, with neighbours on three sides and one narrow way in. Every delivery and every crane lift had to be planned to the hour.
We chose an open-panel timber frame so the shell could go up and be watertight in three weeks. Fernhill Studio led the design, Brookfield Structures detailed the frame, and our crew did the frame, roof, larch cladding and second fix.








WEEK 13
The frame is up and the roof is felted, so the house is now dry inside. The crane comes back on Thursday at 7am for the last lift, and we’ve told the neighbours.
HOW IT WENT
32
weeks, start to snag.
01
Survey & drawings
WK 01–06
02
Groundworks & frame
WK 07–18
03
First fix & roof
WK 19–24
04
Kitchen, joinery & finish
WK 25–32
BEFORE / AFTER




↔
BEFORE
AFTER


“We expected a new build to mean a year of stress, and it simply didn’t. Every Friday we got a note saying what had happened and what was next.”

Mark and Helen Tate
Cranleigh
·
New build


NEXT PROJECT →
Rear extension and kitchen
View project
Let’s build
something solid.
Book a site visit
CALL
01632 960 418
hello@joineryco.co.uk
VISIT
Hurst Farm Yard, Shalford
SOCIAL
Instagram · Houzz
© 2026 JOINERY · DEMO CONTENT
JOINERY


Timber-frame new build
A three-bed timber-frame home on a tight garden plot, built and clad by one crew.
New build
Timber frame
Full build + cladding
Cranleigh
HANDED OVER
32
ON SITE
140 m²
FLOOR AREA ADDED
£350–450k
BUDGET BAND
9
TRADES ON THE JOB
THE BRIEF
A whole house on a narrow plot, watertight before the autumn rain.
Mark and Helen Tate had planning for a family home at the end of a long garden, with neighbours on three sides and one narrow way in. Every delivery and every crane lift had to be planned to the hour.
We chose an open-panel timber frame so the shell could go up and be watertight in three weeks. Fernhill Studio led the design, Brookfield Structures detailed the frame, and our crew did the frame, roof, larch cladding and second fix.








WEEK 13
The frame is up and the roof is felted, so the house is now dry inside. The crane comes back on Thursday at 7am for the last lift, and we’ve told the neighbours.
HOW IT WENT
32
weeks, start to snag.
01
Survey & drawings
WK 01–06
02
Groundworks & frame
WK 07–18
03
First fix & roof
WK 19–24
04
Kitchen, joinery & finish
WK 25–32
BEFORE / AFTER




↔
BEFORE
AFTER

“We expected a new build to mean a year of stress, and it simply didn’t. Every Friday we got a note saying what had happened and what was next.”

Mark and Helen Tate
Cranleigh
·
New build


NEXT PROJECT →
Rear extension and kitchen
View project
Let’s build
something solid.
Book a site visit
CALL
01632 960 418
hello@joineryco.co.uk
VISIT
Hurst Farm Yard, Shalford
SOCIAL
Instagram · Houzz
© 2026 JOINERY · DEMO CONTENT
JOINERY